Electrification and Signalization Projects Conventional Line Construction

Electrification and Signalization Construction Projects Conventional On Line Construction The developments in the signalization and electrification projects that are currently being constructed are as follows;

●● Boğazköprü-Ulukışla-Yenice, Mersin-Yenice, Adana-Toprakkale Electrification and Signaling Project; In this corridor, 99% physical progress has been achieved in the signaling works that have been started to be constructed due to the heavy traffic. With the exception of Mersin-Adana (134 km) section, signaled operations were started in other regions within the scope of the project (447 km). In addition, the electrification works in this sector are continuing and 96% physical progress has been achieved. Adana-Yenice and Niğde-Boğazköprü sections were put into operation.

●● Irmak-Karabük-Zonguldak Electrification and Signaling Project; Rehabilitation and signaling works between Karabük and Zonguldak were completed and put into operation. The electrification project works of the line are under completion.

●● Eskişehir-Kütahya-Balıkesir Signaling and Electrification Project; Signaling and electrification works are in progress. 77% physical progress has been achieved in signaling and Eskişehir-Kütahya (Alayurt), which was completed in the year 2018, was commissioned. 93% physical progress has been achieved in electrification and Eskişehir-Kütahya-Tavşanlı / Tunçbilek line section has been put into operation.

●● Bandırma-Balıkesir-Manisa Electrification and Signaling Project; 76% physical progress was achieved in signaling. Electrification was completed and commissioned.

●● Kayaş-Irmak-Kırıkkale-Çetinkaya Electrification Project; 80% physical progress has been achieved in electrification construction. Şefaatli-Boğazköprü (122km), Boğazköprü-Karaözü and Kayseri North crossing (120 km) and Karaözü-Hanlı (75 km) sections were commissioned.

●● Tekirdağ-Muratlı Signaling and Electrification Project; In the signaling part of the project, testing and commissioning works were completed and commissioned.

●● Konya-Karaman-Ulukışla Electrification and Signaling Project; Electrification works have been completed between Karaman and Konya, and project works are continuing between Karaman and Ulukışla. 20% physical progress has been achieved in signaling between Konya and Karaman.

●● Manisa-Uşak-Afyonkarahisar Electrification and Signaling Project; Electrification construction project works are ongoing. Project works for signaling construction have been completed and tender preparations are continuing.

●● Samsun-Sivas (Kalın) Rehabilitation and Signaling Project; Within the scope of the Modernization Project, the line will be improved and signaling and telecommunication facilities will be installed. Infrastructure and Superstructure acceptance procedures have started. 2018 is planned to be commissioned by the end of the year.